Cumming Street, Brunswick West - Road reconstruction works

Project overview

In 2018-19 Council will be reconstructing Cumming Street, Brusnwick West  between Melville Road and Duggan Street.

Consultation with residents was undertaken in March 2018 and the design was completed in May 2018.

The project is in the Construction phase, with construction works commencing in December 2018 and to be completed in June 2019.

The works comprise:

  • Construction of a new underground drainage system and pits.
  • Reconstructing the existing bluestone kerb and channel.
  • Reconstructing the existing road pavement.
  • Construction of a tree lined median along the road.
  • Laying of a new asphalt road surface.
  • Reconstruction of vehicle crossings between the new kerb and footpath edge.
  • Reinstatement of nature strips.
  • Total length: 380 metres.

Budget and timelines

  • Budget: $1,317,000
  • Construction start date: December 2018
  • Construction end date: June 2019