Holmes-Nicholson-Moreland Shopping Strip

Project backgroundHNM Draft Concept Design

Council is undertaking streetscape improvements to the Holmes-Nicholson-Moreland Shopping Strip, as part of Council’s Shopping Strip Renewal Program.

The aim is to revitalise the area and improve the pedestrian amenity, walkability and presentation of the shopping strip.

Key improvements will include:

  • Footpath upgrade including paving, and kerb and channel
  • Landscaping, including new street trees
  • Upgrade of street furniture
  • Additional bike hoops

The construction phase will commence in May 2018 and conclude in November 2018. The works will be undertaken in stages, to minimise the disruption to the busy intersection.

Budget and timelines

  • Project budget $1million


  • Stage A, B, C - May - September 2018
  • Asphalt Resheeting - October - November 2018

Major stages of the project

Consultation - Complete

A survey was undertaken in November 2016 to seek community feedback on the streetscape improvement.

A report and a one-page summary outlining community feedback from this survey is now available.

Download the

Design - Complete

Feedback received has informed the development of the Final Concept Design Plan (PDF 4Mb) which has sought to address various issues including safety, amenity, and presentation of the streetscape.

Council officers held an Information Session to discuss the community's comments and feedback on the Draft Concept Design, at the Holmes-Nicholson-Moreland Shopping Strip on 21 March 2017.

Construction

Stage 1 is due to commence 30 April and is anticipated to be completed by the end of November 2018.

During construction, access will be maintained to all stores in the shopping centre.

Council is working closely with the contractor to reduce the inconvenience that is inevitably created by any major infrastructure upgrade. However, there will be times when the works will create some unavoidable noise and debris.

We may also need to temporarily modify/divert pedestrian traffic, while the old concrete footpath is being demolished.

Stages

  • Stage A, north-west area of intersection: May – June 2018
  • Stage B, north-east area of intersection: June – July 2018
  • Stage C, south of intersection: July – September 2018
  • Asphalt resheeting of road pavement: October – November 2018

 

Scope and Stages Diagram

 

More information

If you have any queries regarding the project, contact Council’s Senior Urban Designer, Hiren Bhatt on 9240 1234 or email Hiren Bhatt.

 

There are documents on this page in PDF-only format. If you have trouble opening or viewing a PDF document, contact Council and we will arrange to provide the information in a format that suits your needs. See Council's accessibility page for further details.